Digital Infrastructure & Data Centers

Data center programs are constrained less by construction than by power: the date the site can be energized sets every other date on the project, and it is decided by parties the owner does not control.

Project types

Data centers

AI campuses

Powered land development

Medium and high voltage distribution

Cooling and heat rejection plants

Liquid cooling

Backup generation

Battery systems

Campus infrastructure

Commissioning and reliability testing

Where projects fail in this sector

These are the failure modes we see repeatedly. None of them are construction problems.

  • Powered land that is not buildable land

    A capacity letter is not an energization date, and an energization date is not a buildable site. The three get conflated at acquisition and separate painfully afterwards.

  • Utility interconnection assumptions never validated

    The assumption enters the model early, is never independently tested, and is still load-bearing when the capital is committed.

  • Speed-to-energization driving premature design release

    Drawings are released to hold a date rather than because the design is ready, and the rework arrives later at construction prices.

  • Long-lead switchgear and transformer procurement started too late

    The order date, not the construction schedule, is the real constraint — and it is usually discovered after the schedule has been published.

  • Water and cooling strategy decided after site acquisition

    Cooling approach determines water demand, discharge, permitting, and plot area. Deciding it after the land is bought removes the cheapest options.

  • Governance built for a real estate deal, not a mission-critical build

    The decision structure that closed the transaction is rarely the one that can run a commissioning program.